BALINESE GAZEBO FRAME ASSEMBLY INSTRUCTIONS

Step 1

All timbers must be placed and joined with the markings facing up.

Begin by laying the 4 ring beam pieces on a flat area at the location where your Bali Hut is going (these are the widest timbers).

Make sure the ring beams are flat and square, then attach them together using 2 x100mm from one side and 3 x 100mm batten screws from the other side through the face of one beam into the end of the adjoining beam.

Make sure it is square by measuring from corner to corner (the diagonal measurements should both be the same).

                                                             

Step 2

Depending on the size of the post: For example if the posts are 150mm dia. Mark your centre of hole 75mm in from each corner where the ring beams join. Move your ring beam assembly out of the way and dig the four holes 800mm to 900mm deep with diameter of about 450mm.

Once this is done move your ring beam assembly back into place and make sure it is still square and flat.

Next place your posts into the holes you have just dug making sure that both corners of the ring beams are touching the post and are vertical, then set with concrete.

Once the concrete has set you may need to trim the tops of your posts if they are not level with each other. We recommend having the tops of your posts at 2350mm from finished ground / floor level.

Next slide the ring beam assembly up the outside of your posts until the top of the ring beams are 55mm above the tops of your posts.

Then attach your ring beams using 100mm batten screws. If your ring beams are 2m in length you will need 2 screws per side on each post (16 screws altogether), if your ring beams are 3m in length you will need 3 screws per side on each post (24 screws altogether) etc.

 

The Knee braces (not needed if the posts are being concreted into the ground) screw up on the outside of the ring beam, and the outside of the post. Lay the knee brace at 45° across the corner between the post and the ring beam (knee brace sits on the outside of the post and butts up to the underside of the ring beam). Use 2x 50mm batten screws to attach the knee brace into the ring beam, and 2 x 100mm batten screws to attach it to the post, ensuring the post is perpendicular to the ring beam.         

 

For Hip roof go to step 3; for gable roof jump to step 4

 

Step 4 Rafters

Starting with the longest rafters (line marked side faces up) place the lower end against the inside of the ring beam and the top against the hips/ridge beam, pencil lines on the ring beam give an approximate location, check and adjust where necessary using a set square so the rafters are at 90 degrees to the ring beam, the top outer edge of the rafter should be flush with the top of the ring beam.

                                               

 

Screw together using 100mm batten screw through ring beam and 100mm batten screw through top of rafter into hip / ridge beam.

Always start with the longest rafters working to the shortest creepers.

With an A frame roof the rafters are all the same length so do the ends first then after all the rafters are in place attach the brace across the rafters.

Step 3 Hips

When King post is mentioned here substitute it for ridge beam if you have a rectangular kit.

Assemble the hips as follows,

The hips are the double pieces screwed together with point one end and inverse on the other.

Place the pointed end snugly into the upper corner of the ring beam with the line marked side facing up. Ensure top of the hip sides are level with the top of the ring beam hold hip in position while attaching with 2 X 100mm batten screws, screwed through both sides of the ring beam into hip.

The hip will then hold itself in position, repeat for all hips, do not worry if they don’t appear to all line up exactly at this time.

                                               

Insert the King post (square 100mm block) or ridge beam (the large beam made of 2 pieces screwed together with an extension piece of timber on the top) into the center of the 4 hips.

The king post should protrude down about 25mm below the hips, or for ridge beam, the hips should sit 50mm down from the top of the ridge beam main timbers (not the extension timber).

You can then adjust the hips by pushing them up and down until they are all level on the king post / ridge beam. If you end up with 2 diagonally higher than the other 2 your frame is out of square and you need to move the ring beam and posts slightly to adjust them all level

Once they are all lined up screw together with 100mm batten screws.

 

Middle JPG.jpg
20140725_103342.jpg

Step 2.a For installations on concrete slabs.

 

Mark the position of the post on the slab / floor area. Move the frame away. Fit the steel brackets in the post. Put the post on the markers on the concrete slab. Mark the position of the steel brackets on the ground. Remove the steel brackets from the post. Now move the steel brackets back to the marked position. Drill the holes for the draw-bolts. Insert the draw-bolts and fit the steel brackets. Fit the post on the brackets again.

Mark the bottom of the ring beam on all the post.

2150 to 2250 above floor level.

 

Step 2.b For In ground Installations.

 

So if the posts is 150mm diameter mark your center of hole 75mm in from each corner where the ring beams join. Move your ring beam assembly out of the way and dig the four holes 800mm to 900mm deep with diameter of 450mm.

Once this is done move your ring beam assembly back into place and make sure it is still square and flat.

Next place your posts into the holes you have just dug making sure that both corners of the ring beams are touching the post and are vertical, then set with concrete.

Mark the bottom of the ring beam on all the post.

2150 - 2250mm Above floor level.

Step 3

After the post are in and the concrete has set you need to trim the top of the post.

 

Marked the height on the posts that you want the bottom of the ring beam to be installed at. Normally 2150 - 2250mm. Then you need to work out how much to ad to the post before you trim the tops of the posts.

Measure the end of the hips. Subtract that measurement from the with of the ring-beam. eg. If the bottom of the hip is 100mm and the ring-beam is 300mm. 300-100=200mm. So we need to ad 200mm to the mark on our post and then trim the post.

On the small roofs the parameter beam can just be slide up on the outside of the post to the correct height. Attach the ring-beam with 4 ea 100mm batten screws to each end.

On the bigger frames however it is advisable to take the parameter beam apart and install the ring-beam one beam at a time. Use 5ea 100mm batten screws on each end...

Step 4

 

The Knee braces on freestanding Gazebos (not needed if the posts are being concreted into the ground) screw up on the outside of the ring beam, and the outside of the post. Lay the knee brace at 45° across the corner between the post and the ring beam (knee brace sits on the outside of the post and butts up to the underside of the ring beam). Use 1 x 100mm batten screw to attach the knee brace into the ring beam and 1 x 100mm batten screw to attach it to the post, ensuring the post is perpendicular to the ring beam.      

Step 5  

When King post is mentioned here substitute it for ridge beam if you have a rectangular kit. Nr 2 on the plans.

Assemble the hips as follows Nr 3 on plan.

The hips are the double pieces screwed together with point one end and inverse on the other.

Place the pointed end snugly into the upper corner of the ring beam with the line marked side facing up. Ensure top of the hip sides are level with the top of the ring beam hold hip in position while attaching with 2 X 100mm batten screws, screwed through both sides of the ring beam into hip.

The hip will then hold itself in position, repeat for all hips, do not worry if they don’t appear to all line up exactly at this time.

Any problems please call us, we are more than happy to talk you through it.

 

 